23
VAPORSTREAM INSTALLATION, OPERATION, AND MAINTENANCE MANUAL
INSTALLATION
Notes:
• Locate air gap only in spaces with adequate temperature and air movement to absorb flash steam; otherwise, condensation may form on nearby
surfaces. Refer to governing codes for drain pipe size and maximum discharge water temperature.
• Offset humidifier from floor drain to prevent flash steam from rising into the humidifier.
• Dashed lines indicate provided by installer.
• The water supply inlet is more than 1" (25 mm) above the overflow port, eliminating the possibility of backflow or siphoning from the tank. No
additional backflow prevention is required; however, governing codes prevail.
• Damage caused by chloride corrosion is not covered by your DriSteem warranty.
VLC-OM-011
Overview, RO/DI water option
OM-4004
Drain valve
Fill
valve
Skimmer
port
Install level
Install level
¾" (DN20) minimum condensate
drain piping rated for 212 °F (100 °C)
Air vent height
must be equal to
or greater than
dimension H2
(see Table 22-1).
Air vent tube
Steam outlet
¾" (DN20) min. drain overflow piping rated for
212 °F (100 °C)
¾" (DN20) drain valve
If run is over 10' (3 m), increase pipe to 1¼" (DN32)
Flow line of drain piping after water seal must
be below drain valve to ensure humidifier
drains correctly.
1" (25 mm) air gap
Overflow
Strainer, by installer
6"
(150 mm)
minimum
Water supply line; water pressure 25 psi to 80 psi (172 kPa
to 552 kPa); first 3' (1 m) should be stainless steel tubing. To
isolate steam during system maintenance, put a 2" a (50 mm)
water seal or loop in supply line.
Drain piping
flow line
Pitch 1/8"/ft
(1%)
Open drain required. See first note below.
H1
Optional condensate
return piping from
dispersion unit
See H1 in
Table 22-1
mc_022310_1300
mc_030210_1802
¾" pipe thread
(DN20) dispersion
unit condensate
return inlet
Piping:
FIGURE 23-1: FIELD PIPING OVERVIEW, VAPORSTREAM VLC WITH RO/DI WATER OPTION
FIGURE 23-2: PIPING, VAPORSTREAM
VLC WITH RO/DI WATER, MODELS 2-1
THROUGH 5-1