DRI-STEEM Vapormist humidifier • Page 11
Vapormist piping:
DI/RO water
Figure 11-1:
Vapormist (DI/RO water) field piping overview
Unions by installer
Strainer, by installer
¾" pipe thread (DN20) tank
drain, and P-trap piping,
rated for 212 °F (100 °C). If
piping run is over 10' (3 m)
increase pipe to 1¼" (DN32)
after P-trap.
1" (25 mm)
air gap
Spill funnel. Plumb
to floor drain
Frame drain
Cover
Install plumb
DC-1139
First 3' (1 m) of water supply line
should be stainless steel tubing
with a 2" (50 mm) water seal or
loop in the supply line to isolate
steam from nonmetallic supply
piping.
2" (50 mm)
12" (300 mm)
Notes:
• Locate air gap only in spaces with adequate temperature and air movement to absorb flash steam; otherwise, condensation may form on nearby surfaces.
Refer to governing codes for drain pipe size and maximum discharge water temperature.
• Offset humidifier from spill funnel or floor drain to prevent flash steam from rising into the cabinet.
• Dashed lines indicate provided by installer.
• The water supply inlet is more than 1" (25 mm) above the overflow port, eliminating the possibility of backflow or siphoning from the tank. No additional
backflow prevention is required; however, governing codes prevail.
• Install a union in the water supply and drain lines as shown to allow tank removal.
• Damage caused by chloride corrosion is not covered by your DRI-STEEM warranty.
Open drain required.
See first note below.
¾" pipe thread (DN20) frame drain and
P-trap piping, rated for 212 °F (100 °C)
Steam vapor hose (maximum run 10' [3 m]). May also use pipe or
tubing. See the
DRI-STEEM Design Guide
for maximum pipe or tubing
lengths.
mc_042710_1328-VM
Water supply line:
• ¼" NPT (DN8) connection size
• 25 to 80 psi (175 to 550 kPa) required water
pressure.
Commentaires sur ces manuels